The following is an update from WYDOT:

The Y intersection will be milled and paved next week (the week of May 7th - May 13).  Every effort to minimize the impact has been taken. 

The schedule is as follows:

Buffalo Way (from Alpine Lane to Broadway but allowing local traffic to access the bank) will be closed from Tuesday night (May 8) through to the end of paving.   Weather permitting the paving will be completed by Sunday night (May 13).   

Milling will take place on Tuesday and Wednesday nights starting at 7:00pm and will run until 6:00am.  Ramps will be left for traffic to use during the day.

Paving - Paving Broadway is scheduled to begin on Thursday (May 10). Single lane traffic with the intersection under 24 hour flagger control.  No paving on Friday as tests are run on pavement.  Paving will continue throughout the weekend.   

WYDOT is advising people to avoid the Y intersection on Thursday and over the weekend.  

If you have any questions please contact:

Bob Hammond, P.E.

Resident Engineer

WYDOT - Jackson, WY

Direct - (307) 732-9602

Office - (307) 733-3665

 